This shows you the differences between two versions of the page.
Both sides previous revision Previous revision Next revision | Previous revision Next revision Both sides next revision | ||
chara:power_recovery [2020/10/29 14:07] gail_stargazer |
chara:power_recovery [2021/08/26 11:00] gail_stargazer |
||
---|---|---|---|
Line 1: | Line 1: | ||
October 27, 2020 | October 27, 2020 | ||
- | Things Judit had to do in the lab **to recover after power outage** | + | Things Judit had to do in the lab **to recover after power outage:** |
- | * Shutters | + | * Shutters |
- | * Home Newport stage VIS beams (same as Esp BC2 gui VISB axis) | + | * Homed Newport stage VIS beams (same as Esp BC2 gui VISB axis) |
- | * Bootlaunch | + | * Bootlaunch_master |
- | * Home Newport | + | * Homed all 6 Newport |
* Labao DM electronics were all fine, all those UPSes kept the power | * Labao DM electronics were all fine, all those UPSes kept the power | ||
* Started up labao computer | * Started up labao computer | ||
- | * Pushed power button on the USB hub for labao cameras before starting labao servers so that the servers could find the cameras | + | * Pushed power button on the USB hub for labao cameras |
* Labao shutters were OK, on same UPSes as labao DM | * Labao shutters were OK, on same UPSes as labao DM | ||
* Cycled ApertureWheels power and inited all 6 Aperture Wheels | * Cycled ApertureWheels power and inited all 6 Aperture Wheels | ||
* Started up tiptilt computer → check was forced due to not clean shutdown | * Started up tiptilt computer → check was forced due to not clean shutdown | ||
* Soft rebooted tiptilt computer with entering BIOS and RE-SAVED it for proper clock start | * Soft rebooted tiptilt computer with entering BIOS and RE-SAVED it for proper clock start | ||
- | * Homed all axes of Titlit | + | * Homed all axes of tiptilt |
- | * All pops were out and PERI postions | + | * All pops were out and PERI positions |
- | * Irimage computer was off → I restarted | + | |
+ | Additional Notes After Power Outage on August, 17, 2021 | ||
+ | |||
+ | * Reinitialize the NIRO Filter Wheel. Open the niro_filter_gtk and click REINIT. Check to see if the indicator wheel on the NIRO camera is pointing to the correct filter after it is homed. Do not turn the wheel by hand. If it points to the wrong filter, home the filter wheel again, and compare counts for each filter (or look for metrology light in J-band) | ||
+ | * Leave plenty of time to do a full check of the alignment on all beams. | ||
+ | * Check alignment of MIRC-X and MYSTIC using STS. Make sure the fiber stages and internal delays are consistent with the positions recorded in the manual/ | ||
+ | * Home the engineering beam using BC1. A list of engineering beam positions for each beam is on a post-it note near the stage. Note that CLIMB_B1 and CLIMB_B2 are usually not homed and just left in their last good positions. If they are homed, the fringe positions for the CLIMB1 stages: CL1= 7.0565 mm and CL2 = 5.3224 mm. For the CLIMB2 stages: CL4= 2.9630 mm and CL5= 7.8500 mm. (See email from Judit on Aug 8, 2021.) | ||
+ | * Home and re-align lab tiptilt zaber stages. See the {{: | ||
+ | * Check the PAVO ENG GUI to see if the PAVO zaber stages lost position. If so, prior to the next run, follow instructions in the [[: | ||